[에너지신문] 16 February 2016 -  US energy group NRJ Energy's Canal-3 power project has cleared the ISO-New England 10th forward capacity auction at a price of US$7.03/kW-month.
The Canal-3 project will be a 333 MW gas turbine peaker, developed on Cape Cod, on the site of the existing Canal Station in Sandwich, Massachusetts (United States). Capital investments will start in 2017 with significant development expenditures in 2018. The project is expected to be commissioned in 2019 and will operate mainly during peak demand periods or in the event of unexpected outages.

http://www.enerdata.net/enerdatauk/press-and-publication/energy-news-001/nrj-energy-plans-333-mw-gas-turbine-peaker-cape-coad-us_36148.html

저작권자 © 에너지신문 무단전재 및 재배포 금지