[에너지신문] Lead contractor GAMA Power Systems has selected Black & Veatch to replace turbines at the 1,156 MW Hamitabat CCGT power plant in Turkey. Four combined cycle turbine (2-on-1) units will become two single shaft units. Both units will use the latest Siemens 50 Hz H-class combustion turbines together with new steam turbines to generate approximately a total of 1,200 MW. The replacement will simplify operations while improving generation efficiency, from about 38% to 62%. It is expected to be completed in the second half of 2017.
The 1,156 MW Hamitabat power plant was commissioned between 1985 and 1989 in the Kirklareli region by national power utility EUAS.

http://www.enerdata.net/enerdatauk/press-and-publication/energy-news-001/12-gw-hamitabat-ccgt-power-plant-will-be-modernised-turkey_33077.html